What is the correct order of steps in finishing standard-weight concrete slabs?

Prepare for the GERTC Master of Science in Sanitary Engineering Test. Study with our multiple choice questions and detailed explanations. Succeed in your exam!

The correct order of steps in finishing standard-weight concrete slabs is critical to ensuring a good finish and usability of the surface. The sequence begins with screeding, which entails leveling the fresh concrete to the desired elevation, removing excess material to create a flat surface. Following this, the concrete must be leveled, ensuring that the slab has an even thickness and that it meets necessary specifications and tolerances.

After leveling, edging is performed to create clean, rounded edges along the sides of the slab, which helps to prevent chipping and provides a nice, finished look. Jointing is the next step, where control joints are cut into the slab to help manage cracking caused by temperature changes and settling.

The process of troweling comes next, which further smooths the concrete surface and compacts it, providing a more durable finish. Floating then follows, where a tool is used to bring some of the slurry to the surface, further smoothing the concrete and preparing it for the final finish. Finally, broom finishing is employed to create a textured surface for improved traction.

This sequence ensures that each step is performed in a logical manner that contributes to the overall quality and functionality of the concrete slab. The other options do not include all necessary steps in the correct order